Pickleball/Basketball Project Updates
Updates will be posted regularly to keep you up to date on our exciting project!
Scope of Project: 6 Regulation Sized Pickleball Courts and a Basketball Court (Full Court)
4/15/20
- WSN staked the project site to develop a Grading & Paving Plan.
4/20/20
- Holden Electric removed a light pole located within the project site.
5/4/20
- Underground utilities were located.
5/7/20
- Anderson Brothers broke ground, signifying the official start of the project. They cut material in the morning and started on the aggregate base (class 5) in the afternoon.
5/8/20
- Anderson Brothers completed construction of the aggregate base in preparation for the bituminous base course (first lift).
5/13/20
- Anderson Brothers started and finished the bituminous base course.
5/14/20
- Anderson Brothers applied tack to the base course in preparation for the wear course.
- Anderson Brothers started and finished the wear course.
5/22/20
- Elite Fence & Deck started driving posts for the fence.
5/30/20
- Elite Fence & Deck finished installing the fence on the courts.
6/17/20
- Maintenance Staff poured concrete footings for the basketball hoops
6/22/20
- Lee Sports Surfacing pressure washed the playing surface of each court.
6/23/20
- Lee Sports filled "bird baths" and began applying the base acrylic material.
6/24/20
- Lee Sports finished applying the base material and started to apply layers of the green acrylic.
6/25/20
- Lee Sports finished applying the acrylic surfacing and began taping for striping the lines.
- Lee Sports finished striping the pickleball courts
6/26/20
- Lee Sports started and finished striping the the basketball court.
6/29/20
- Park Staff assembled the basketball hoops
7/1/20
- City representatives and other important members gathered to cut a ribbon - signifying the grand opening of the new pickleball and basketball facility.